 I have thiings to do list in a different format:

  
Things to doPriorityDelegated ToCompletion DateNext ReviewCompeted DateType

Stock Take HighSelf22-Apr-08Daily
Review

Research on Email Web InterfaceHighSelf22-Apr-08
22-Apr-08ResearchFound Many Commercial version
HPUX - Unix Training preparation PlanningHighSelf22-Apr-0821-Apr-08
Plan

Create startup and shutdown script for oraasHighSelf18-Apr-08




Research on Email Exchange
ServerHighSelf23-Apr-0822-Apr-0822-Apr-08ResearchFound Citadel with web
interface
MailScanner for Internal EmailHighPeter23-Apr-0822-Apr-08
Peter had problem with his comp

Stock Take Reports require by DrastantHighSelf25-Apr-08Daily
Preliminaries in place

Stock Take integration file generation module req. by
kashyapHighSelf25-Apr-08

Basic structure in place

Hardware Team orientation with Activity List and Delegation
formHighSelf19-Apr-08Postpond
Orientation










Things to doPriorityDelegated ToCompletion DateNext ReviewCompeted DateType

Enligthen Team of CitadelMIDSelf30-Apr-08Daily
Orientation

HPUX - Unix Training preparation PlanningLOWSelf22-Apr-0821-Apr-08
Plan

Create startup and shutdown script for oraasMIDSelf18-Apr-08




MailScanner for Internal EmailHighPeter23-Apr-0822-Apr-08
Peter had problem with his comp

Stock Take Reports require by
DrastantHighSelf25-Apr-08Daily23-Apr-08Completed by drastant, to ignore, as
per my conversation with drastant.

Stock Take integration file generation module req. by
kashyapHighSelf25-Apr-08
23-Apr-08Dos Version Complete

Hardware Team orientation with Activity List and Delegation
formHighSelf19-Apr-08Postpond
Orientation

Plan Presentations techniques for DBA TeamMIDTeam15-May-0826-Apr-08
Orientation



















 

And There is a delegation form for each item delegated to team/person:

  
Action Delegation Form For: Manish Chudasama

Date Delegated:15 April 2008
TaskCreate Version Control History For ORMS - Upgrades and Backup Complete









Purpose AndMake complete backup of nhlret server, including system files.
Create a version control history
Contextthat will show all the updates and patches applied to RMS and RDW
database and ORESA

Indicate Date and Activity Carried out for that date.












Completion Date16 April 2008
Specific GoalsTo keep track of all the changes for next upgrade and roll off
for Production instance from Test 

Instance, Backup complete on Sunday the 20Th April 2008, for safety as it is
we are also

Backing up today, and to take extra precaution, we backup on Sunday as well.






Check PointReport any difficulties directly to kashyap, treat this as a top
priority.
& ReportingTuesday evening to discuss and review the report.

Handover the complete document Wednesday 16th April 2008



SupportEmail, Database etc...
& Resources




Additional NotesJot down from emails all the recommendation from enabler
team.












 

Is this possible for the groupware to be integrated with things to do list,
with the above format.  This will turn out to be a MIS solution in that case,
as time management principals are incorporated.

Kind Regards