Would you be interested in sharing your solution? 

> On 9 Jan 2015, at 11:10, Siaynoq <siaynoqm...@gmail.com> wrote:
> 
> What we did was on the "runner", e.g. TestNG level, meaning we iterated 
> through the example table and created/started X Scenarios with only one 
> specific example table row. It's actually much simpler than it sounds with 
> the help of JBehave functions.
> 
> Zoltan
> 
>> On Thu, Jan 8, 2015 at 10:14 PM, Mauro Talevi <mauro.tal...@aquilonia.org> 
>> wrote:
>> Hi,
>> 
>> there is currently no way to parallelise the running of the scenarios 
>> parametrised in the examples table, because the concurrency is managed at 
>> story level. 
>> 
>> You could break down your 50+ examples in smaller scenarios and       run 
>> them as different stories. 
>> 
>> Cheers
>> 
>>> On 07/01/2015 08:50, Venkatesh Laguduva wrote:
>>> Hi,
>>>     I have a story file with 50+ examples listed below in the table and it 
>>> takes really a lot of time; is there a way to run these examples in 
>>> parallel? if not, what would be the best approach to reduce the execution 
>>> time?
>>> 
>>> Thanks
>>> Venkatesh Laguduva
> 