The below schedule was scheduled for 1 PM.  The client scheduler is
polling and at 1:05 PM it updated, and said the schedule would start in 33
minutes.  What causes a schedule to execute a time later than scheduled?  I
am aware of staggered starts for scheduled events, but this is the only
thing scheduled at this time and nothing else is running on the server.  Any
ideas?

Thanks,
Jon Martin


Policy Domain Name: SOLARIS
Schedule Name: REBUILD_MR
Description: Daily backup for Solaris Clients
Action: Incremental
Options:
Objects: /rebuild_mr/ATX1/
Priority: 1
Start Date/Time: 05/16/01   13:00:00
Duration: 12 Hour(s)
Period: 1 Day(s)
Day of Week: Tuesday
Expiration:
Last Update by (administrator): ADMIN
Last Update Date/Time: 07/09/02   10:57:07
Managing profile:



07/09/02   13:05:12
------------------------------------------------------------
07/09/02   13:05:12 Schedule Name:         REBUILD_MR
07/09/02   13:05:12 Action:                Incremental
07/09/02   13:05:12 Objects:               /rebuild_mr/ATX1/
07/09/02   13:05:12 Options:
07/09/02   13:05:12 Server Window Start:   13:00:00 on 07/09/02
07/09/02   13:05:12
------------------------------------------------------------
07/09/02   13:05:12 Command will be executed in 33 minutes.
07/09/02   13:05:12

Reply via email to