Deal, but it’s all rock :-)

Mark

> On Jan 3, 2019, at 11:37 AM, [email protected] wrote:
> 
> I will do two miles of directional drilling for $13.50/foot  $142K
>  
> From: Ken Hohhof <>
> Sent: Thursday, January 3, 2019 9:32 AM
> To: 'AnimalFarm Microwave Users Group' <>
> Subject: Re: [AFMUG] Why some places don't have broadband yet
>  
> At that price, it seems you could put up 2 miles of brand new poles and then 
> charge somebody else make ready and pole attachment fees when they want to 
> string cables.
>  
> You should keep an eye out to make sure they don’t give a much better price 
> to some telco in the future, I think they are required to charge WISPs the 
> same pole attachment fees as anybody else, or does that not cover make ready 
> costs?  I do suppose make ready costs depend on circumstances, but seriously, 
>  $50 per foot of road?  Assuming one pole every 300 feet, that’s maybe 40 
> poles, so $15K per pole?  Somebody wants you to pay for all new poles.  Or 
> more likely, they just don’t want to do it.
>  
> From: AF <[email protected] <mailto:[email protected]>> On Behalf 
> Of Chuck Hogg
> Sent: Thursday, January 3, 2019 9:59 AM
> To: AnimalFarm Microwave Users Group <[email protected] 
> <mailto:[email protected]>>
> Subject: Re: [AFMUG] Why some places don't have broadband yet
>  
> One time I built a the last bit for AT&T to avoid their build-out costs.
>  
> We're currently building a section for Windstream to expedite the build and 
> reduce costs.
>  
> On Thu, Jan 3, 2019 at 10:48 AM < <>[email protected] <mailto:[email protected]>> 
> wrote:
>> Go rent a cable plow.  If it is good plowing you will only need it for a day 
>> or two.
>> Cable plow rental = perhaps $2000
>> Cable and conduit & misc= $7500
>> 
>> You have 8 customers for $10K
>> Say  you get $50/customer, or $400 per month or $4800 per year...
>> 
>> Who doesn't want 48% return on their money?
>> 
>> 
>> -----Original Message----- 
>> From: Adam Moffett
>> Sent: Wednesday, January 2, 2019 10:21 PM
>> To:  <>[email protected] <mailto:[email protected]>
>> Subject: [AFMUG] Why some places don't have broadband yet
>> 
>> I just got a quote for make-ready on a 2 mile stretch.
>> $593,000
>> 
>> I guess those 8 households will remain unserved because eff that.
>> 
>> 
>> -- 
>> AF mailing list
>>  <>[email protected] <mailto:[email protected]>
>> http://af.afmug.com/mailman/listinfo/af_af.afmug.com 
>> <http://af.afmug.com/mailman/listinfo/af_af.afmug.com> 
>> 
>> 
>> -- 
>> AF mailing list
>>  <>[email protected] <mailto:[email protected]>
>> http://af.afmug.com/mailman/listinfo/af_af.afmug.com 
>> <http://af.afmug.com/mailman/listinfo/af_af.afmug.com>
> 
>  
> -- 
> Regards,
> Chuck
> 
> -- 
> AF mailing list
> [email protected] <mailto:[email protected]>
> http://af.afmug.com/mailman/listinfo/af_af.afmug.com 
> <http://af.afmug.com/mailman/listinfo/af_af.afmug.com>
> -- 
> AF mailing list
> [email protected] <mailto:[email protected]>
> http://af.afmug.com/mailman/listinfo/af_af.afmug.com 
> <http://af.afmug.com/mailman/listinfo/af_af.afmug.com>
-- 
AF mailing list
[email protected]
http://af.afmug.com/mailman/listinfo/af_af.afmug.com

Reply via email to