Yes, they are...we are heading back at 12:30...with drawings and background
from original engineer.

On Thu, Jun 3, 2021, 11:18 AM Jan-GAMs <[email protected]> wrote:

> What's that two inch conduit at bottom right corner of right-hand
> cabinet?  Is that the 480 incoming?
> On 6/2/21 1:09 PM, Bill Prince wrote:
>
> That's a virtual switch. Does not need a physical connection to operate.
>
> I also don't particularly like the routing of the 480V cables. Would have
> preferred they cam in via a separate conduit, but maybe that's just me.
>
>
> bp
> <part15sbs{at}gmail{dot}com>
>
> On 6/2/2021 11:23 AM, Jaime Solorza wrote:
>
> Look above where 480 comes in....the handle!!!!! They removed it bypassing
> safety design to keep idiots from getting fried...
>
> On Wed, Jun 2, 2021, 10:54 AM Jaime Solorza <[email protected]>
> wrote:
>
>> We just got hired to troubleshoot several lift station issues with VFDs,
>> pumps and connectivity drop outs at Fort Bliss....we did not design any of
>> these enclosures....they are sending us drawings and tech with lock out
>> keys couldn't meet us until tomorrow...
>>
>>
>>
>
> --
> AF mailing list
> [email protected]
> http://af.afmug.com/mailman/listinfo/af_af.afmug.com
>
-- 
AF mailing list
[email protected]
http://af.afmug.com/mailman/listinfo/af_af.afmug.com

Reply via email to