Look at mean well pb-1000-48. We just installed one, working fine so far.
On Jan 5, 2015 6:06 PM, "Adam Moffett" <[email protected]> wrote:

>
> Most of the equipment is 48v, so I'd want to stick with 48v if possible.
> 260 Watt is the minimum, but it's possible future load could go up to
> 500Watt.  I'll check out Traco, thanks!
>
>  How much more do you need?  Traco TSP series has units that scale up to
>> 600w at 24V if you want to stick with a DIN mountable solution.
>>
>>  On Jan 5, 2015, at 5:54 PM, Adam Moffett <[email protected]> wrote:
>>>
>>> I've used the meanwell AD-155C for lots of small sites, but I have to
>>> set up some soon that will require a lot more than 155Watts.
>>>
>>> What are my options without spending a zillion dollars on a rectifier?
>>> I was actually looking at pairing a beefy 48v supply with a solar
>>> controller, but I'm wondering about the longevity and reliability of that.
>>>
>>>
>>>
>