In California not to crazy. just depends on where it is. if its in rock or an urban area It could have cost a pretty penny to build. It as well could be on low strand count fiber so you have to eat more of the cost. I have seen a build in an urban environment be 500k a km. Its more likely though that they just want you to go away. I have seen some quotes for 100k just to put in 3 splice tails on an existing IRU. Sometimes it has to do with permitting. One of them happened to be on railroad property....

On 3/7/2016 6:23 PM, TJ Trout wrote:
They want $4k monthly "O&M" with a 500k "20 year IRU"

Don't really understand this

On Mon, Mar 7, 2016 at 3:42 PM, Eric Kuhnke <[email protected]
<mailto:[email protected]>> wrote:

    500k NRC is them saying to you "go away and stop bothering us any
    further".



    On Mon, Mar 7, 2016 at 3:33 PM, TJ Trout <[email protected]
    <mailto:[email protected]>> wrote:

        Local lec quoted me 4k mrc for 2 strands DF with a 500k NRC but
        no build is involved?  Is this legit?