Yes, are inside and outside crews were offset 1-2 days on scheduling.
Different crews doing different parts, with a floater crew that could do
both.

On Mar 6, 2017 7:31 PM, "Craig Schmaderer" <[email protected]> wrote:

> This might only answer half your question but we don't install a customer
> until the entire pon cabinet is done, main line all done and main cross
> splice cases are done.  (About 250 houses usually is the size) So if its a
> new install drop and that handhole doesn't have a splice in yet (because
> this is the first of 4-6 drop handhole) so I would say it takes at least
> 4-6 man hours to do this.  We usually will have a drop crew install the
> drop a day before and splice everything up to the house. Than our wireless
> installers install inside the house the next days. Drop guys get durty and
> usually its hard to guess how long a drop will take so we have found it
> easier for the inside installer to come later.
>
>
> ------------------------------
> *From:* Af <[email protected]> on behalf of Paul Stewart <
> [email protected]>
> *Sent:* Monday, March 6, 2017 7:03:15 PM
> *To:* [email protected]
> *Subject:* Re: [AFMUG] Fiber Build Time Question
>
> Thanks - that helps for sure…. I came up with 4 hours per dwelling on
> average from start to finish to have the service on the curb and ready to
> pull in …
>
> Basically, in a situation where have permits, locates, engineering and
> everything in place - now guys go! :)  Then as orders come in, then
> “installation” happens and I figured 4 hours there as well doing one off
> installs
>
> Really rough and as you know lots of factors but it doesn’t seem my
> estimate is far off
>
> Thanks,
> Paul
>
>
>
> > On Mar 6, 2017, at 6:37 PM, Chuck McCown <[email protected]> wrote:
> >
> > That's what happens when you don't actually read the post....
> >
> > We provide the duct if the developer provides the trench, so that part
> is pretty quick.  Handholes are installed later.  Probably a half hour per
> dwelling for empty duct and handholes.
> >
> > Then we pull and splice.  Add another hour per dwelling.
> >
> > Then we hang the ONT and install.  Probably 3 hours per dwelling.  But
> that is doing them in volume with a crew of 4-6 guys.
> >
> >
> > -----Original Message----- From: Paul Stewart
> > Sent: Monday, March 06, 2017 4:21 PM
> > To: [email protected]
> > Subject: Re: [AFMUG] Fiber Build Time Question
> >
> > 80% of what? :)  I’m trying to calculate man hours …
> >
> > Thanks,
> > Paul
> >
> >> On Mar 6, 2017, at 6:18 PM, Chuck McCown <[email protected]> wrote:
> >>
> >> 80%
> >>
> >> -----Original Message----- From: Paul Stewart
> >> Sent: Monday, March 06, 2017 4:15 PM
> >> To: Animal Farm
> >> Subject: [AFMUG] Fiber Build Time Question
> >>
> >> I checked around and can’t come up with a number so asking the list ….
> it’s an open ended question I realize…
> >>
> >> For every 1000 homes passed, assuming a medium density deployment
> (meaning primarily houses in subdivisions but limited MDU) - how much time
> to trench the fiber and have connectivity ready to then run the drop to a
> customer premise when they order service?  I’m trying to calculate the man
> hours involved with going down a street and having everything ready for
> service leaving out the CPE/drop side of things.
> >>
> >> Cheers,
> >> Paul
> >>
> >>
> >
> >
>
>
>

Reply via email to