So you guys convinced me to build on the dirt, much easier. Now what is the
smallest span of guys I can get away with? I want to do 12 sections of 25G
and I can guy it 3 or 4 times, I'm assuming 4 is better. I really want to
keep the guys in as close as possible to save the valuable farming space I
have, so what is the guy span from the tower base that would be recommended
? "how low can i go?" (without making any safety issues, this tower will
only have 4 sectors and a 2ft dish at 40ft).

Thanks,

TJ

On Sun, Mar 25, 2018 at 3:32 AM, Lewis Bergman <[email protected]>
wrote:

> I would tell you that you are waisting money. 2 sections are going to cost
> you a lot less and be a better long term solution than mounting a tower on
> a building. You can use a house bracket near the top depending on your
> building design and start your guy calculations from that point.
>
>
> On Tue, Mar 20, 2018, 9:22 PM TJ Trout <[email protected]> wrote:
>
>> I'm building a 40x40 or possibly 50x60 steel building. I would like to
>> install a guyed 25g on the peak (about 20ft peak from ground level with
>> 16ft walls)
>>
>> If I guy off 4 times how high can I go?
>>
>> Any way to do 100ft or ten sections ? I'm assuming my guy span isn't far
>> out enough.....
>>
>> I know what's on the drawings but I am looking for some real world
>> feedback....
>>
>> Thank you very much
>>
>> TJ
>>
>

Reply via email to