Hi,

When closing a sprint and transferring remaining tasks to the next
sprint, I noticed that the burndown chart of the closed sprint
suddenly showed zero hours at the end. Is this intentional? I don't
like this kind of "history rewrite." This brings up the question of
how the burndown is calculated. I suspect that it only takes the
current state into account. It would probably be more correct to take
the ticket_change table into account. When tasks are moved to the next
sprint, their associated remaining time would be subtracted from the
burndown at that point in time. If the time of moving is after the
sprint has been closed, the burndown for that sprint would not change.

Regards,
Knut
--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to