(just going through old support mails, looks like you did not receive an answer yet - sorry about that).

Am 14.08.2009 22:10, schrieb Issam:
The problem is if a task is linked to a requirement then its remaining
time is not calculated.

I could go around the code (which I understood a litle before 0.8) and
find why are the remaining time of these tasks is not being calculated
in the total time.  But I was hoping someone might have seen this and
made a fix, or could point me to a quick fix.

I guess you need to copy the default calculated property definition from user stories to requirements. For syntax help, see:
https://dev.agile42.com/agilo-help/admin/typeadmin#CalculatedProperties