(just going through old support mails, looks like you did not receive an answer yet - sorry about that).
Am 14.08.2009 22:10, schrieb Issam:
The problem is if a task is linked to a requirement then its remaining time is not calculated. I could go around the code (which I understood a litle before 0.8) and find why are the remaining time of these tasks is not being calculated in the total time. But I was hoping someone might have seen this and made a fix, or could point me to a quick fix.
I guess you need to copy the default calculated property definition from user stories to requirements. For syntax help, see:
https://dev.agile42.com/agilo-help/admin/typeadmin#CalculatedProperties fs
smime.p7s
Description: S/MIME Cryptographic Signature