On Dec 7, 11:26 am, "Dennis P. Nikolaenko" <[email protected]> wrote: > And how capacity for the sprint is going to calculated? > Imagine the person is a member of two teams and, say, has 40 hours of > work per week. > There are two parallel sprints assigned to these teams. 40 hours have to > be split somehow between the sprints. > How? Proportionally? Manually? > How to track contingents?
Well, you can already assign capacity/hours for a team member. Simply split it any way you want. I think it is really valid to have people in multiple teams, especially in small companies where one person can wear multiple heads. For example, I might mainly work on a the backend of a product at thus belong to the "backend team", but sometimes the UI team needs me to do a task for them, so I should be able to get a few hours for that team in a given sprint. Contingents are measured in the sprint you mainly work on. Regards, Stephan -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum ----- You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en