On 15 Jan, 2010, at 12:39 , Jan Torben Heuer wrote:
> Hi,
Hi Jan,
> is there some remaining time per user view available? When adding more user
> stories to the backlog it'd be nice to see who has still capacity.
Did you try to have a look in the Team Statistics for that specific Sprint?
There on top there is a table that shows what is the current load per Team
Member, and shows in "red" those who have a higher load than their capacity...
Is that what you need?
> Cheers,
Ciao
> Jan
ANdreaT
--