Hi and thanks for the help.

I proceeded exactly in the order given by installation and
configuration guide, AGILO Quickstart in Help/Guide. As I don´t have
any experiences with SCRUM (ok except the small things you learn
during studdiing, but that doesn´t really count) I stuck to your
guides and explanation materials.

In the meanhwile, upon the 4th installation, I still have the same
problem. I can get the product backlog to work, when I delete the
default ones at the beginning and then create new ones. Though
sometimes I am not able to configure a created backlog. When I add it,
sometimes it opens up the configuration page (description, global or
sprint, etc.), but only approx. 1 out of 10 times. The other nine
times it creates a gloabl backlog. Most of the time I am also not able
to edit the existing backlog.

I got a product backlog to work, I got a milestone backlog to work,
but still the sprint backlog doesn´t want to work. That was in the
third installation, now in the 4th everything is not working again. I
am not able to reproduce at least getting product and milestone to
work again.

I cannot provide any other user information, as I am the only user for
now. But I used a team member account and it is the same.

By "you created a currently running sprint before?", do you mean that
I created a sprint with a starting date before the current date? It is
possible that I did that, but that was on first installation. Is that
something I shouldn´t have done or not do at all? Error on my side?

I would be glad to send you the project. Any special adress to send
too or just yours?

Thank you very much again, higly appreciated, thanks.


On Jan 15, 3:52 pm, Felix Schwarz <[email protected]> wrote:
> Hi there,
>
> this looks very strange. However I was unable to reproduce the problem.
> Can you descripbe your process on a step-by-step basis? Please also
> describe what your preconditions are (you created a currently running
> sprint before?)
>
> Can you check if other users in your Agilo have the same problem?
> If that doesn't help, please send us your environment folder so we can
> have a look on our machines.
>
> fs
>
>  smime.p7s
> 4KViewDownload
-- 
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
-----
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en

Reply via email to