Am 03.02.10 16:01, schrieb Craig Griffin:
> Hello,
> We're attempting to define our product backlog as anything not
> assigned to a sprint. We have stories that are clearly part of a
> Milestone, while others may or may not be, we will discuss with the
> client and decide later.
> However the 'strict' setting eliminates those stories that are
> assigned to a Milestone (but not a sprint). If we uncheck 'strict,'
> then the backlog includes everything in sprints as well. The stories
> assigned to a sprint have already been discussed (and developed), so
> it is confusing to have those included for review.
> Is it possible to create a backlog that shows all stories not assigned
> to a sprint (only)?

Well... its not strictly possible, but there might be a workaround that
could help you.

You can manually enable the setting

-- snip --
[agilo-general]
backlog_filter_attribute = sprint
-- snap --

Which will show a filter popup in the backlog that you can use to filter
out everyting that has a sprint assigned.

Then a non-strict product backlog might do what you want.

Please tell if that helps you! (I haven't tried this yet)

Regards,
Martin

-- 
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
-----
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en

Reply via email to