Hey Mark, On Tuesday 06 July 2010, Mark wrote: > I am 3 Sprints into using Agilo and my pain point so far has been > that the burndown chart functionality is not working for me. All I > see is a light blue line for Actual Burndown that advances everyday > but stuck at zero. I don't see any other lines.
Are you planning stories and tasks for the sprint? Do the tasks have a remaining time (as estimated at the sprint planning/task breakdown -- this is needed to raise the actual burndown above zero)? Do you have a team associated to the sprint, does the team have members (for the capacity bar)? Do you use the confirm commitment button at the start of the sprint (in order to calculate ideal burndown correctly)? Cheers Robert -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum Please support us by reviewing and voting on: http://userstories.com/products/8-agilo-for-scrum http://ohloh.net/p/agilo-scrum http://freshmeat.net/projects/agiloforscrum You have received this message because you are subscribed to the "Agilo for Scrum" Google Group. This group is focused on supporting Agilo for Scrum users and is moderated by agile42 GmbH <http://www.agile42.com>. To post to this group, send email to [email protected] To unsubscribe from this group, send an email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo

