Hey Alex!

On 11/04/11 16.17, alejandrovk wrote:
I can't seem to find the meaning of this in any of the documentation
links. What is the meaning of it? Estimated hours to accomplish the
taks?

What units are accepted? days, hours, person/month?
This is the number of estimated remaining hours to complete the task. So this starts out as the total amount of work (e.g., 10 hours), but it is good practice to reduce it when you stop working on a task (e.g, at the end of the day) to the amount of work still remaining (e.g., 4 hours).
That way, you get meaningful burndown data for the next day's standup ;-)
When the task is completed, remaining time is 0.

If you want to use days instead of hours for estimation, you can do that by setting use_days_for_time = True in trac.ini.

Besides, is there a way to relate a task to a requirement? kinda the
same way I do with User Story-Requirement?
You can relate tasks to requirements by following these steps:
1. Login as TRAC_ADMIN
2. Go to the "Admin" page
3. Click on "Links" in the left panel
4. In the "Add Link" you can select "Requirement" as Source and "Task" as Target

What kind of tasks would you link to a requirement though?


Cheers

Stefano

--
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
Please support us by reviewing and voting on: http://userstories.com/products/8-agilo-for-scrum http://ohloh.net/p/agilo-scrum http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Scrum" Google Group. This group is focused on
supporting Agilo for Scrum users and is moderated by
Agilo Software GmbH <http://www.agiloforscrum.com>.

To post to this group, send email to [email protected]
To unsubscribe from this group, send an email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo

Reply via email to