Hi Udit,
On 03/05/11 10.50, udit chopra wrote:
There were 4 pending tasks in the SPRINT 2 and SPRINT 2 was finished.
I went into TIMELINE and Tried CLOSING the SPRINT 2
It asks to move the pending 4 tasks to other sprint , so i
selected SPRINT 3
And it resulted in this error.
thanks for your collaboration. We also need the stack trace to analyze the
problem thoroughly, can you please provide us with that?
Cheers
Stefano Rago
--
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-scrum
http://freshmeat.net/projects/agiloforscrum
You have received this message because you are subscribed to
the "Agilo for Scrum" Google Group. This group is focused on
supporting Agilo for Scrum users and is moderated by
Agilo Software GmbH <http://www.agiloforscrum.com>.
To post to this group, send email to [email protected]
To unsubscribe from this group, send an email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo