Maneesh,
Thanks for your reply.
They were set up like that by an outside contracting firm. My "availability" 
time segment has a level of 3 associated to it and my "unavailability" time 
segment has a level of 4.

The below statement is taken from the ARS 7.1 Configuring Guide:

Understanding levels
Levels define a priority between different time segments, and a higher level 
time
segment takes precedence over lower-level time segments. Levels can be from 1 to
1000.
Levels 1 and 2 have special meaning. Level 1 time segments are "available" and
can be used to define workdays. Level 2 time segments are "unavailable" and can
be used to define holidays. Other time segments at Level 3 and above can be 
either
"available" or "unavailable."
NOTE
Because higher levels of available segments can override Level 2 time segments, 
if
you do not want to override holidays, define holidays at a level higher than all
other levels.

I don't understand why it is not working..

Marcelo

-----Original Message-----
From: Action Request System discussion list(ARSList) 
[mailto:[email protected]] On Behalf Of Maneesh Gotiya
Sent: Tuesday, September 07, 2010 11:03 AM
To: [email protected]
Subject: Re: Business Time Segments

Hi,

Why are you setting segment as level 4 unavailability?. Make it level 1
it will work as required.

maneesh

-----Original Message-----
From: Action Request System discussion list(ARSList)
[mailto:[email protected]] On Behalf Of Martinez, Marcelo A
Sent: Tuesday, September 07, 2010 8:55 PM
To: [email protected]
Subject: Business Time Segments

Yesterday was a holiday (Labor Day) in the U.S. Today, as I get back to
work this I find that many incident tickets which carry SLA service
targets have either missed their target or have escalated (fired its
milestones). Many of these incidents were submitted yesterday..

I have configured Business Time Segments and one of them is for Labor
Day; set up as level 4 Unavailability. I also have defined available and
unavailable times which my company deems as "working hours".  I have
checked the "Shared Entity/Segments" (SLM:ConfigBusinessEntityConsole)
and made sure that the time segment is related to my company (entity). I
have checked my service targets and made sure that they are using the
Business Entity of "My Company" in the Business Schedules field.

Therefore I've checked my time segments, I've checked that time segments
are part of the business entity, and I've checked that the service
targets are using the business entity for business times.

Despite of all the above, it looks like my service targets are ignoring
my holiday business time segments. I am currently running a filter log
to find out what is causing this behavior. If anyone has any
suggestions, please advise.

ARS7.1
ITSM 7.0.03
SLM 7.0 P4

Thanks,
Marcelo

________________________________________________________________________
_______
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"

Please do not print this email unless it is absolutely necessary. 

The information contained in this electronic message and any attachments to 
this message are intended for the exclusive use of the addressee(s) and may 
contain proprietary, confidential or privileged information. If you are not the 
intended recipient, you should not disseminate, distribute or copy this e-mail. 
Please notify the sender immediately and destroy all copies of this message and 
any attachments. 

WARNING: Computer viruses can be transmitted via email. The recipient should 
check this email and any attachments for the presence of viruses. The company 
accepts no liability for any damage caused by any virus transmitted by this 
email. 

www.wipro.com

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"

Reply via email to