Can some one please tell me what all parameters do I need to set to e 
happening execute my production order automatically ie. directly from 
started to finish and also from created to reported as finish.

In my set up I am trying to finish a started PO. Whats happening is 
that when I go to report as finished then the system says that my job 
are not reported as finished. It forces me to coarted mplete the jobs 
in a journal and only then allows me to finish, cost and end a PO. I 
am posting my routes automatically at start up. What else do I need 
to do to report the order finished automatically from started as well 
as created.

Also, one more. I have a demo ver, my machine date is 5/1/2004 and my 
system data is the current date. What is machine date? This field is 
seen in Tools->System Date. 

Please help here asap.

Thanks



------------------------ Yahoo! Groups Sponsor --------------------~--> 
Make a clean sweep of pop-up ads. Yahoo! Companion Toolbar.
Now with Pop-Up Blocker. Get it for free!
http://us.click.yahoo.com/L5YrjA/eSIIAA/yQLSAA/kGEolB/TM
--------------------------------------------------------------------~-> 

Sharing the knowledge on Axapta. 
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/Axapta-Knowledge-Village/

<*> To unsubscribe from this group, send an email to:
    [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/
 

Reply via email to