Will this also consider the lead time of the Items as specified for the item type / service type items in the item master. Say if i have an item X of type item that is required and is not avialabe will the lead time be considered
On Tue, Apr 1, 2008 at 12:56 PM, Anders Sorensen <[EMAIL PROTECTED]> wrote: > Hi, > > > > If the Finite material checkbox is selected, then it means that an > explosion is run on the production before performing the job scheduling. If > the sub components of the production BOM are all on hand then it has no > impact on the scheduling, but if some items are not on hand and a planned > order has been made for those items, then the scheduling will start from the > Futures date of the planned orders. > > > > Hope this answers your questions, otherwise look in the help file for the > Job scheduling form where it is explained pretty good. > > > > Regards, > > Anders > > > > > > This posting is provided "AS IS" with no warranties, and confers no > rights. > > *From:* visti Sethna [mailto:[EMAIL PROTECTED] > *Sent:* 1. april 2008 07:11 > *To:* Axapta-Knowledge-Village@yahoogroups.com; Anders Sorensen; thurmalla > nagesh > *Subject:* Re: [Axapta-Knowledge-Village] Lead Time in planning for > Scheduling of operations > > > > > Sir can you tell me what are the effects of ticking the finite material > checkbox. and what will the implications be. > > > > Reply ASAP > > Regards > > Visti > > > > > > > On Mon, Mar 31, 2008 at 7:28 PM, Anders Sorensen <[EMAIL PROTECTED]> > wrote: > > The checkbox for finite material can be found on the General tab of Job > Scheduling or Operation Scheduling forms (Production - > Production orders > -> Update -> Job scheduling). > > > > Regards, > > Anders Sorensen > > > > > > This posting is provided "AS IS" with no warranties, and confers no > rights. > > > > > > *From:* Axapta-Knowledge-Village@yahoogroups.com [mailto: > [EMAIL PROTECTED] *On Behalf Of *visti Sethna > *Sent:* 31. marts 2008 07:35 > *To:* Axapta-Knowledge-Village@yahoogroups.com > *Subject:* [Axapta-Knowledge-Village] Lead Time in planning for Scheduling > of operations > > > > Can someone tell me how will the time be captured for the subcontracting > (Service type) item please. Coz My gant chart should capture the lead time > for procurement of the subcontracted item when I schedule the jobs. > Instead, it schedules the first operation instantly after the second > operation. There is something called finite material and finite capacity > planing. Where do i select the checkbox for finite material planning. > > > > Please suggest. > > > -- > With Regards, > Mr. Vishtaspa Sethna > Associate E.R.P. Consultant > Godrej Infotech Ltd. > Cell: +919718010823 > > > > > > > -- > With Regards, > Mr. Vishtaspa Sethna > Associate E.R.P. Consultant > Godrej Infotech Ltd. > Cell: +919718010823 > -- With Regards, Mr. Vishtaspa Sethna Associate E.R.P. Consultant Godrej Infotech Ltd. Cell: +919718010823