Dear Tushar

You can do it with task group.

Regards
Kusman
Primacom, Jakarta.
www.myprimacom.com

On Sun, Oct 11, 2009 at 1:34 PM, Tushar Joshi <tushar_s_jo...@yahoo.co.in>wrote:

>
>
> Hi All,
>
> Item of type "BOM" has a ROUTE defined for it which sets the sequence of
> the tasks to be performed to manufacture a finished product. In every route
> a work center group or a work center can be attached for one operation.
>
> But Is it possible to create a route where one operation will have more
> than one work centers assigned to it?? Also is it possible to define a
> priority of utilization of the work center?
>
> Example - Item BOM has a route R1 defined for it. In Operations the Op1 is
> performed on M/c 1 but at the same time it can also be done on M/c 2 and M/c
> 3 so I want tos et these 3 machines for one operation and also want to
> define the priority that which work center should be used first (during
> production scheduling or work center capacity reservations) if all 3 are
> available.
>
> I am aware that in Std AX 2009 we can not assign more than 1 work centers
> for an operation, but is it possible to customize it? will it affect the
> core functionality of AX?
>
> Your suggestions will be of gr8 help!
>
> -Tushar
>
> ------------------------------