Hi, try to set the fallback principle of the costing version to Active.
Best regards Michael From: S Hasan bukhari Sent: Saturday, October 24, 2009 1:18 PM To: Axapta-Knowledge-Village@yahoogroups.com Subject: [Axapta-Knowledge-Village] BOM Calculation Costing - Urgent Dear All, The BOM Calculation picks the Items costs defined in the Costing Versions which is a standard cost. But i dont want to use the Cost Price based on the Stock Model not on the basis of Costing versions.if i have not defined the item cost price in Costing version , while running the BOM calculation AX is giving the message Cost Price is Zero. Please reply as soon as possible Regards, Hasan Bukhari