Hi all, I have this problem with Axis2 and ADB. My wsdl schema defines some dates elements:
... <xs:element name="datefrom" type="xs:date"/> <xs:element name="dateto" type="xs:date"/> .. It seems,there must be smth wrong in parsing dates in Axis2. when I send <datefrom>2004-07-27</datefrom> <dateto>2007-07-27</dateto> I get 27.7.2004 27.7.2007 so it s correct. Some other examples and these are interesting: 1. <datefrom>2004-07-270</datefrom> is after parsing 2004-07-27(seems it always takes first 10 symbols and tries to parse it) 2. <datefrom>2004-07-207</datefrom> is after parsing 2004-07-20 3.(example with wrong date) <datefrom>2004-07-41</datefrom> is after parsing 10.8.2004 (seems like it counts it in this way -> 41 - 31(max day date in July) = 10 (.8.2004) So I think, it should get some error and not to parse in this date or can I make with it smth else? Thanks Vladi