So, I have been playing with cloning and I have it working, where i have 
a job that sends the clone to a volume in a different pool using the 
line below in a job directive, and that seems to work ok.

Run = "host1 level=$l since=\"$s\" Pool=DefaultClone"

The schedule for this job is a Full on fridays and differentials each 
other day.

What I really want to do is run the clone only after a Full backup, so I 
will have a separate tape on monday with the Full backup to be sent 
offsite. I do not see a way to do this? Suggestions? Am I missing a 
useful directive?

Thanks
Bob

-------------------------------------------------------------------------