> Objet : [Farsides] [Hackit] [Code] week Oct 28 - Nov 4 estimation
> 
> Hi
> I looked at the tasks needed to integrate the missions into the
> frontend of hackit (alpha 2.1). I think a more accurate estimation
> would be 4 days instead of 3.
> I'm finishing the OO unit tests and the cleaning up of files today and
> start with the missions on Monday morning and it will be ready on
> Thursday evening.
> If i manage to finish it in 3 days i'll go right ahead with the bugs
> for alpha 2.0
> 

[David] Works for me Vlad, thanks - I updated
http://farsides.com/wiki/Tasks_follow-up accordingly

_______________________________________________
Farsides mailing list - [email protected]

Wiki:  http://farsides.com/
List:  http://farsides.com/ml/
Forum: http://farsides.com/forum/
Ideas: http://farsides.com/ideas/
Chat:  http://farsides.com/chat/

Reply via email to