Anyone see a problem with the below plan? The goal is to upgrade our BES 4.1 system without compromising our existing passive BES4.1 failover server for any length of time.
Set up two VM's for BES 5. One is the passive for high-availability. Migrate users from BES4.1 physical server to active BES5 VM. Wipe the BES4.1 machine and install BES5 from scratch. Also wipe the other BES4.1 physical failover server Disjoin the passive BES5 VM from the active BES5 VM. Attach the active BES5 VM to the newly installed physical BES5 server. Manually fail the users over from the active BES5 VM to the passive BES5 physical server. Disjoin the BES5 VM (now passive). Attach the Active BES5 physical server to the newly installed BES5 physical passive server.
_______________________________________________ Bes-Admins mailing list [email protected] http://www.dataoutages.com/mailman/listinfo/bes-admins http://www.dataoutages.com http://www.dataoutagenews.com RSS Feed: http://feeds.feedburner.com/Bes-admins --------------------------------- Bes-Admins mailing list is sponsored by Dataoutagenews.com. http://www.dataoutagenews.com