Here is the schedule!  Yippee!

Brickline will start the markings this week.  Mega Rentals will be removing the 
existing skips. 

The phasing of construction will be:


July 29th to Aug 1st

1.  Remove white skips

2.  Mark the bike lane lines and TWLTL lines

3.  Remove the centerline

4.  Mark the left turn arrows

5.  Place barrels as temporary islands

 
A couple weeks later depending on crew availability

6.  Install islands and bus pads (this will take about 2 weeks)


Mike Rewey

--------------------------------------------------
On 29 Jul 2013 at 21:48, Patrick Lenon wrote:

In happier news, the bike lanes are being painted on North Sherman Ave. today. 
Let
the culture wars commence! ;)