Weekly Update for the Milwaukee St. / Fair Oaks Ave. Intersection and Bridge 
project

For the week starting Monday November 9, 2015:

The Milwaukee Street Bridge east of Fair Oaks Ave. will be reopened Monday 
November 9th sometime late in the afternoon or evening.   The contractors will 
continue working on the project through November 20th to finish and cleanup any 
remaining work needing to be completed.

The intersection will continue to be controlled by stop signs until the new 
signals are operational.

The Madison Metro Transit bus routes will resume service to the area on 
Wednesday November 11th.

https://www.cityofmadison.com/engineering/projects/milwaukee-street-bridge-at-starkweather-creek

Arthur Ross, Pedestrian-Bicycle Coordinator
City of Madison Traffic Engineering Division
215 Martin Luther King, Jr. Blvd., Suite 100
PO Box 2986
Madison, WI  53701-2986
608/266-6225