Phase 3, planned for 2020, from Seminole Highway to the Verona Road
frontage road, is delayed until 2020 specifically so that storm water
engineering plans can be completed. Two big problems to solve:
1. Sheet flow over the Cap City State Trail between the Velo UnderRound
and the Dawley Bike Hub connecting path leading to marshy conditions in
good weather and ice hazards in winter
2. Transporting storm water during "gully washer" events from the ponds
to the west safely past the roundabout to Dunn's Marsh
The roundabout will be redesigned and rebuilt during this process. I
don't know what the new design will look like, but I hope we still have
the unique roundabout.
On 11/21/2019 1:37 PM, Jim Wilson via Bikies wrote:
From what I understand there are plans to improve drainage,
particularly at the bike roundabout.
On Thu, Nov 21, 2019, 12:21 Darin Burleigh via Bikies
<[email protected] <mailto:[email protected]>> wrote:
I finally got back to the newly repaved section of the Capitol City
trail - nice!
I think they will be continuing with the section west of Seminole Hwy.
Does anyone know if they will be addressing the permanently swampy
area ?
darin burleigh--
Steve Arnold, Former Mayor
2530 Targhee Street, Fitchburg, Wisconsin 53711-5491
Telephone +1 608 278 7700 · Facsimile +1 608 278 7701
[email protected] · http://Arnold.US
Support my work: like http://facebook.com/SteveArnoldforMayor.
_______________________________________________
Bikies mailing list
[email protected]
http://lists.danenet.org/listinfo.cgi/bikies-danenet.org