@Antony Why did you set this defect in that case to "Invalid"? If you see the 
point made like you did in your latest comment please reopen then.
B.t.w. it is not a feature as you call it, it is functionality that should be 
in a serious ERP. In my opinion for performance reasons there should be a 
manual trigger on the top BOM item and a automic action via the scheduler 
before the MRP run is executed. That way no extra module is needed and it could 
be implemented in standard.

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/702288

Title:
  Cost price calculation limited to 2 levels in product bom

Status in OpenERP Modules (addons):
  Invalid

Bug description:
  A concrete example better than a long and difficult explanation :-)

  We have the following product A composed of the product B and product B is 
composed from product C. So the below BOM:
  A
  -----B
  -----------C

  If the price of B is modified, then the price of A can be also modified.
  But if i modify the price of C, only B is modified and not A.

  This is a very important blocking issue, since in most of the real prod 
environment, we've of course more than 2 level of boms (in some customer 
installation, up to 100 levels !).
  So any modification at the bottom should have a consequence on all the bom 
structure until the top, else OpenERP cannot be used for production.

_______________________________________________
Mailing list: https://launchpad.net/~c2c-oerpscenario
Post to     : [email protected]
Unsubscribe : https://launchpad.net/~c2c-oerpscenario
More help   : https://help.launchpad.net/ListHelp

Reply via email to