Hi, I was hoping that you will find a way to leave it writable, but fix the re-scheduling of the work orders, it would be very hard for us to not be able to do that.
As a workaround, after you change the order's date, we press the "Change QTY" button and the workorders get re-scheduled. We have a flexible production mode, and also lots of thing can go bad, we make a lot of testing on the products, so it happens often that not all the work scheduled for a day is finished, so we need to re-schedule often. Please do not make it read only, but find a more elegant way of rescheduling. Thanks! -- You received this bug notification because you are a member of C2C OERPScenario, which is subscribed to the OpenERP Project Group. https://bugs.launchpad.net/bugs/805503 Title: mrp - moving an MO to another day does not change the workorders date and time Status in OpenERP Modules (addons): Confirmed Bug description: I go to a MO and change the date from 01.07.2011 to 20.07.2011 But the workorders still remain in the 01.07.2011. I understand that moving a workorder does not change the MO date, but I believe that changing MO start date should reschedule all the workorders start date. Thanks To manage notifications about this bug go to: https://bugs.launchpad.net/openobject-addons/+bug/805503/+subscriptions _______________________________________________ Mailing list: https://launchpad.net/~c2c-oerpscenario Post to : [email protected] Unsubscribe : https://launchpad.net/~c2c-oerpscenario More help : https://help.launchpad.net/ListHelp