Try the project trigger: http://ccnetlive.thoughtworks.com/ccnet/doc/CCNET/Project%20Trigger.html
You can set the trigger condition (triggerStatus) for the fail/success condition. Craig -----Original Message----- From: [email protected] [mailto:[email protected]] On Behalf Of Mark Huggins Sent: Friday, 30 January 2009 3:36 a.m. To: ccnet-user Subject: [ccnet-user] Work flow question. I'm relatively new to ccnet and I need to set up some dependent projects so that if Project A fails it will kick off Project B if Project B builds successfully then Project A will kick off again. If Project B fails it then needs to email and not attempt to rebuild Project A. I've been running through the docs but can't seem to find a solution