Hi,
I'm trying to find some suggestions on what could be going on here, as
I can't seem to work out exactly what's happening. Sometimes a
scheduled task will run, sometimes not. The configuration for a
particular task is as follows:
<scheduleTrigger name="nightly" time="19:00"
buildCondition="ForceBuild">
<weekDays>
<weekDay>Monday</weekDay>
<weekDay>Tuesday</weekDay>
<weekDay>Wednesday</weekDay>
<weekDay>Thursday</weekDay>
<weekDay>Friday</weekDay>
</weekDays>
</scheduleTrigger>
When I got in this morning (on the 5th), I saw that the last build was
on the 3rd at 7pm (which is a day it should have built, as that's a
Monday), and the next scheduled build was for the 5th at 7pm. It
seemed to have completely skipped over Tuesday.
I have gone over the past 3 weeks and it has typically been running 3
times a week on unpredictable days.
We were having issues just before Christmas with some other tasks not
building, but that seemed to have fixed itself up over the New Year
break, though I'm presuming it's all related.
Any suggestions would be greatly appreciated.
Regards,
Josh.