lets say I have certain dates (x) and (y)

now I do a ((x) - (y)) in oracle and I get a number like 18.12 or 18.82

I was doing a round of the result above which yielded me 18 or 19 based on
the percentile. While I was expecting 19 always, the ceil function helped me
to achieve that.

Hope that helps clarify the question... More of a rounding issue.

-----Original Message-----
From: Alex [mailto:[EMAIL PROTECTED]]
Sent: Tuesday, August 20, 2002 10:10 AM
To: CF-Talk
Subject: Re: days between function in Oracle...


ceiling() will round up

What's your question ...days beween dates or rounding?

On Tue, 20 Aug 2002, Alex Ninan wrote:

> Hi,
>
> Does anyone know of a function I can use to get the number of days between
2
> dates in Oracle. My basic problem is I can get the dates but on using the
> round function it's screws up...
>
> e.g
> round(18.12) = 18 days
> round(18.82) = 19 days
>
> What I want is a function which does
>
> function(18.12) = 19 days
> function(18.82) = 19 days
>
> Thanks
>
> Alex
>
> 

______________________________________________________________________
Your ad could be here. Monies from ads go to support these lists and provide more 
resources for the community. http://www.fusionauthority.com/ads.cfm
FAQ: http://www.thenetprofits.co.uk/coldfusion/faq
Archives: http://www.mail-archive.com/[email protected]/
Unsubscribe: http://www.houseoffusion.com/index.cfm?sidebar=lists

Reply via email to