Hi Stephen,

you wrote:
> 
> Whenever I request a date in the period 31/3/08 to 7/4/08 it’s out by an 
> hour hence it causes problems with all my reports for that period.
> 
> E.g.  31/3/08 becomes 30/3/08 at 11pm.
> 
>  > 
> Was there a fix for the daylight saving in Australia, I have the latest 
> JVM being 1.4.2_11 .

Two questions can be asked from the server end of things:-
1. Does the server run daylight savings at all? Many hosting shops 
don't, it's +10 here all the time.

2. If it does run daylight savings was the MS patch done? This year MS 
got caught short and the patch was not a compulsory one so unless the 
admin deliberately put it in then its not there.


-- 

Yours,

Kym Kovan