https://issues.apache.org/jira/browse/AIRFLOW-3542?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Dan Davydov resolved AIRFLOW-3542.
----------------------------------
    Fix Version/s: 1.10.0
       Resolution: Fixed

> next_ds semantics broken for manually triggered runs
> ----------------------------------------------------
>
>                 Key: AIRFLOW-3542
>                 URL: https://issues.apache.org/jira/browse/AIRFLOW-3542
>             Project: Apache Airflow
>          Issue Type: Bug
>          Components: scheduler
>    Affects Versions: 1.10.2
>            Reporter: Dan Davydov
>            Assignee: Dan Davydov
>            Priority: Major
>             Fix For: 1.10.0
>
>
> {color:#222222}next_ds{color}{color:#222222} is useful when you need 
> cron-style scheduling, e.g. a task that runs for date "X" uses that date for 
> its logic, e.g. send an email to users saying the run that was supposed to 
> run for date "X" has completed. The problem is it doesn't behave as expected 
> when it comes to manually triggered runs as illustrated by the diagrams 
> below.{color}
>  
> Using execution_date in a task
> *Scheduled Run (works as expected)*
> execution_date1           start_date1
> \/                                  \/
>  *|-----------------------------|*
> /\                                  /\
>  \_________________/
>    scheduling_interval
>  
> *Manual Run* *(works as expected)*
> triggered_date + execution_date + start_date
> \/
> *|*
>  
> Using next_ds in a Task
> *Scheduled Run (works as expected)*
> next_ds1 + start_date1           next_ds2 + start_date2
> \/                                                         \/
>  *|------------------------------------------------|*
> /\                                                         /\
>  \____________________________/
>              scheduling_interval
>  
> *Manual Run* *(next_ds1 is expected to match triggered_date as in the case 
> for the manually triggered run that uses the regular execution_date above)*
> triggered_date                                    next_ds1 + start_date
> \/                                                         \/
> *|-------------------------------------------------|*
> /\                                                         /\
>  \____________________________/
>              0 to scheduling_interval (depending on when the next execution 
> date is)
> Proposal
> Have next_ds always set to execution_date for manually triggered runs instead 
> of the next schedule-interval aligned execution date.
>  
> This _might_ break backwards compatibility for some users but it can be 
> argued that the current functionality is a bug. If it's really desired we can 
> create new aliases that behave logically although I am against this.
>  
> prev_ds should probably also be made consistent with this logic.



--