Prashant Wason created HUDI-2285:
------------------------------------

             Summary: Metadata Table Synchronous Design
                 Key: HUDI-2285
                 URL: https://issues.apache.org/jira/browse/HUDI-2285
             Project: Apache Hudi
          Issue Type: Task
            Reporter: Prashant Wason
            Assignee: Prashant Wason


h2. *Motivation*

HUDI Metadata Table version 1 (0.7 release) supports file-listing optimization. 
We intend to add support for additional information - record-level index(UUID), 
column indexes (column range index) to the metadata table. This requires 
re-architecting the table design for large scale (50billion+ records), 
synchronous operations and to reduce the reader-side overhead.
 # Limit the amount of sync requirement on the reader side
 # Syncing on reader side may negate the benefits of the secondary index 
 # Not syncing on the reader-side simplifies design and reduces testing


 # Allow moving to a multi-writer design with operations running in separate 
pipelines
 # E.g. Clustering / Clean / Backfills in separate pipelines


 # Ease of debugging 
 # Scale - Should be able to handle very large inserts - millions of keys, 
thousands of datafiles written

 
h3. *Writer Side*

The lifecycle of a HUDI operation will be as listed below. The example below 
shows COMMIT operation but the steps apply for all types of operations.
 # SparkHoodieWriteClient.commit(...) is called by ingestion process at time T1
 # Create requested instant t1.commit.requested
 # Create inflight instant t1.commit.inflight
 # Perform the write of RDD into the dataset and create the HoodieCommitMetadata
 # HoodieMetadataTableWriter.update(CommitMetadata, t1, WriteStatus)
 # This will perform a delta-commit into the HUDI Metadata Table updating the 
file listing, record-level index (future) and column indexes (future) together 
from the data collected in the WriteStatus.
 # This commit will complete before the commit started on the dataset will 
complete.
 # This will create the t1.deltacommit on the Metadata Table.
 # Since Metadata Table has inline clean and inline compaction, those 
additional operations may also take place at this time


 # Complete the commit by creating t1.commit

Inline-compaction will only compact those log blocks which can be deemed 
readable as per the algorithm described in the reader-side in the next section.
h3. *Reader Side*
 # List the dataset to find all completed instants - e.g. t1.commit, t2.commit 
… t10.commit
 # Since these instants are completed, their related metadata has already been 
written to the metadata table as part of respective deltacommits - 
t1.deltacommit, t2.deltacommit … t10.deltacommit


 # Find the last completed instant on the dataset - t10.commit
 # Open the FileSlice on the metadata partition with the following constraints:
 # Any base file with time > t10 cannot be used
 # Any log blocks whose timestamp is not in the list of completed instants (#1 
above) cannot be used


 # Only in ingestion failure cases the latest base file (created due to 
compaction) or some log blocks may have to be neglected. In success cases, this 
process should not add extra overhead except for listing the dataset.



--