https://issues.apache.org/jira/browse/NIFI-1198?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Bryan Bende updated NIFI-1198:
------------------------------
    Description: I had connected several processors in a line and had them all 
valid and ready to be started. I then decide to remove one processor from the 
path, so lets say I had Proc1 connected to Proc2 connected to Proc3. I deleted 
the connection between Proc2 and Proc3, then dragged the existing connection 
between Proc1 and Proc2 to make it go from Proc1 to Proc3. At this point 
everything should have been valid, but Proc3 said it was invalid because it 
required input. If I deleted this connection and created a new one between 
Proc1 and Proc3 then all was good.   (was: I had connected several processors 
in a line and had them all valid and ready to be started. I then decide to 
remove one processor from the path, so lets say I had Proc1 connected to Proc2 
connected to Proc3. I deleted the connection between Proc2 and Proc3, then 
dragged the existing between Proc1 and Proc2 to make it go from Proc1 to Proc3. 
At this point everything should have been valid, but Proc3 said it was invalid 
because it required input. If I deleted this connection and created a new one 
between Proc1 and Proc3 then all was good. )

> Processor InputRequirement indicating invalid when it should be valid
> ---------------------------------------------------------------------
>
>                 Key: NIFI-1198
>                 URL: https://issues.apache.org/jira/browse/NIFI-1198
>             Project: Apache NiFi
>          Issue Type: Bug
>    Affects Versions: 0.4.0
>            Reporter: Bryan Bende
>            Priority: Minor
>             Fix For: 0.4.0
>
>
> I had connected several processors in a line and had them all valid and ready 
> to be started. I then decide to remove one processor from the path, so lets 
> say I had Proc1 connected to Proc2 connected to Proc3. I deleted the 
> connection between Proc2 and Proc3, then dragged the existing connection 
> between Proc1 and Proc2 to make it go from Proc1 to Proc3. At this point 
> everything should have been valid, but Proc3 said it was invalid because it 
> required input. If I deleted this connection and created a new one between 
> Proc1 and Proc3 then all was good. 



--
This message was sent by Atlassian JIRA
(v6.3.4#6332)

Reply via email to