+This RFC proposes that TVM move to a quarterly release schedule. Releases 
would happen every 3 months or so on a schedule set well in advance, 
independent of individual feature development in TVM.
+
+# Motivation
+Releases are essential to the usage of TVM, especially now that are beginning 
to work on publishing binary packages for TVM under PyPi. Making TVM releases 
frequent forces the release process to become well documented and simple rather 
than bespoke and only achievable by a small group. Users benefit from releases 
by seeing that the the project is still under active development and providing 
an easy way to get new features. As of this RFC it has been five months since 
the last release. It could easily confuse new users when they expect some TVM 
feature that was only developed recently but is not present in the latest 
official release.
+
+
+# Guide-level explanation
+TVM has [release process 
documentation](https://tvm.apache.org/docs/contribute/release_process.html). 
This RFC proposes that a release candidate vote thread sent on a schedule 
roughly every three months. A release branch will be cut, evaluated for a 
period of two weeks, evaluated by the PMC, then a release published. Publishing 
a release entails:
+
+* Gathering and organizing release notes since the last release
+* Posting a source code release on GitHub
+* Uploading the source code to the Apache SVN repository
+* Uploading binary packages to tlcpack
+* Uploading binary packages to PyPi
+* Getting an approval vote from the PMC
+
+# Reference-level explanation
+
+Prior to a release a new, lightweight vote would instead be used to nominate a 
release manager, a committer who will be responsible for guiding along the 
release process. Releases will roughly match the quarterly [calendar 
dates](https://en.wikipedia.org/wiki/Calendar_year#Quarters) shifted two weeks 
earlier (Q1: mid March, Q2: mid June, Q3: mid September, Q4: mid December). The 
release manager will have final say on all dates and consideration should be 
given for their personal schedule. The timeline will be as follows:
+
+* Three weeks prior to the release
+    * The release manager will cut a release branch and create a new tag
+    * The release manager will audit the licenses of all project dependencies 
to ensure they are compatible with Apache
+    * The release manager will open a GitHub issue announcing the release 
branch cut and target date for the release and state that any further 
inclusions in the release must be manually cherry-picked
+    * The release manager will create a PR targeted to merge into the release 
branch with the necessary changes to make a release (i.e. changing version 
numbers)
+    * Contributors that wish changes to be cherry-picked should comment on the 
announcement issue with the relevant PRs and commits and their reasoning. The 
release manager has final say on which changes should be included but should 
aim to be inclusive at this stage
+    * The release manager begins gathering release notes
+
+* Two weeks prior to release
+    * Cherry picks become limited to critical changes only
+    * The release manager begins building binaries and testing them against 
TVM's test suite
+    * The release manager sends the release notes and plan to a vote thread 
for approval (feedback thread will be open for one week)
+    * The release manager performs another license audit of all project 
dependencies to ensure they are compatible with Apache
+
+* One week prior to release
+    * The release manager sends the release and binaries to a vote thread for 
approval (thread open for one week). If rejected the building and test process 
must be started anew and repeated until the PMC approves.
+
+* Day of the release
+    * The release manager publishes the relevant binaries
+    * The release manager closes the release issue
+    * The release manager makes a GitHub release and updates an in-repo file 
`RELEASE.md` on both `main` and the release branch with the release notes
+
+Much of this can be automated via GitHub Actions on the apache/tvm repo. 
Eventually (though maybe not for the upcoming release) these will handle all 
the building, testing, and publishing of releases so the job of the release 
manager will become simpler over time.
+
+The release manager will use the release notes and discussions with developers 
to determine the next version number. Releases will continue the current 
versioning scheme of `major.minor.patch`, with a typical release involving a 
bump of the minor release version. Patch versions will be used for follow up 
releases onto a quarterly release, but not for the next quarter's release. The 
release manager will be responsible for maintaining the release until the next 
release, which mainly entails putting up a patch release if necessary. The 
release manager may also delegate this responsibility to another party if both 
agree.

Review Comment:
   agree semver is probably too much for us right now and we should revisit at 
1.0. Increasing version numbers seem simplest to think about which is what this 
RFC proposes and anecdotally date releases aren't as common for Python packages 
(though they are listed in [PEP 440](https://peps.python.org/pep-0440/))



-- 
This is an automated message from the Apache Git Service.
To respond to the message, please log on to GitHub and use the
URL above to go to the specific comment.

To unsubscribe, e-mail: [email protected]

For queries about this service, please contact Infrastructure at:
[email protected]

Reply via email to