Map/Reduce would benefit too from the extended date (Sept 18). I still
think Owen's latest proposal is more suitable.
Tsz Wo (Nicholas), Sze wrote:
seems that the Nigel's previous suggestion (i.e. append Sept 18, others Sept
4) is better.
For your reference, attached the previous message thread "[VOTE] Push back code
freeze for 0.21" at the end .
Nicholas Sze
----- Original Message ----
From: Nigel Daley <nda...@yahoo-inc.com>
To: common-dev@hadoop.apache.org
Sent: Thursday, August 13, 2009 2:23:24 PM
Subject: Re: [VOTE] Freeze date for Common, HDFS, and MapReduce 0.21
+1
On Aug 12, 2009, at 4:04 PM, Owen O'Malley wrote:
All,
After the discussion settled last time, it seems that HDFS needs more time
to settle append and sync. Therefore, I'd like to propose a freeze time of 4:30
pst on 18 Sep for making the 0.21 branch for Common, HDFS, and MapReduce.
-- Owen
From: Eric Baldeschwieler <eri...@yahoo-inc.com>
To: common-dev@hadoop.apache.org
Sent: Friday, July 24, 2009 5:11:15 PM
Subject: Re: [VOTE] Push back code freeze for 0.21
AGGHH!
Let's not push out the general freeze even as far as sept 4th if
possible. I'd suggest oct 31st. If we push out the general freeze
until append is complete, we will delay having a stable release with
append at least an additional month.
E14
From: Nigel Daley
Date: Fri, 24 Jul 2009 16:30:55 -0700
To:
Subject: Re: [VOTE] Push back code freeze for 0.21
There's a 3rd option I'd support. Feature freeze on Sept 4, except
for Append which gets a 2 week extension. This allows us to start
stabilizing the rest of the code base while Append is finished up.
Nige
On Jul 24, 2009, at 4:25 PM, Konstantin Boudnik wrote:
I second Konstantin's point: FI tests are likely to take a pretty
hefty chunk of overall dev. time. Considering that people'd be
facing a certain learning curve to master this new technology we are
likely to need more time for the completion of the development of
the code & tests.
+1 for farther push back, e.g. until 9/18/09
Konstantin (aka Cos)
On 7/24/09 4:18 PM, Konstantin Shvachko wrote:
I would like to clarify the append plans.
Right now according to our planning schedule we need about
8 weeks to complete the implementation of the design.
This will include all the functionality and unit testing
according to the test plan.
September 4 deadline gives us about 6 weeks to commit the features.
Which is 2 weeks short off our schedule.
This of course if the implementation will not go much faster than
we predicted :-).
So, we can either move the freeze a couple of weeks further ahead.
Or we can also use some help from the people familiar with the
design.
E.g. there is a lot of hours scheduled to unit test writing using
fault
injection, etc.
Thanks,
--Konstantin
Amr Awadallah wrote:
+1 for stable append.
-- amr
Dhruba Borthakur wrote:
+1
On 7/24/09, Jim Kellerman
(POWERSET) wrote:
+1
-----Original Message-----
From: Owen O'Malley [mailto:omal...@apache.org]
Sent: Friday, July 24, 2009 1:11 PM
To: common-dev@hadoop.apache.org
Subject: [VOTE] Push back code freeze for 0.21
I'd like to push the date for the code freeze back to 4
September to
give the file append more time to be finished well. Clearly,
I'm +1.
-- Owen
--
With best regards,
Konstantin Boudnik (aka Cos)
Yahoo! Grid Computing
+1 (408) 349-4049
2CAC 8312 4870 D885 8616 6115 220F 6980 1F27 E622
Attention! Streams of consciousness are disallowed
------ End of Forwarded Message
----- Original Message ----
----- Original Message ----
From: Nigel Daley <nda...@yahoo-inc.com>
To: common-dev@hadoop.apache.org
Sent: Thursday, August 13, 2009 2:23:24 PM
Subject: Re: [VOTE] Freeze date for Common, HDFS, and MapReduce 0.21
+1
On Aug 12, 2009, at 4:04 PM, Owen O'Malley wrote:
All,
After the discussion settled last time, it seems that HDFS needs more time
to settle append and sync. Therefore, I'd like to propose a freeze time of 4:30
pst on 18 Sep for making the 0.21 branch for Common, HDFS, and MapReduce.
-- Owen