2 is ok

other values for state are:
2=ok
3=failure
4=error
6=building
7=checking out
8=updating

Emmanuel

Artamonov, Juri a écrit :
Emmanuel,

You always saying "you need to modify the project state" but never saying on 
what vakue it should be changed.

Ok, what correct value should be for the projects? I see all projects' state set to 
"2", is it ok?

Juri.


-----Original Message-----
From: Emmanuel Venisse [mailto:[EMAIL PROTECTED] Sent: Wednesday, August 30, 2006 9:38 AM
To: [email protected]
Subject: Re: Continuum thinks a build is running


If the workaround doens't work, you need to modify the project state in database with a sql client like Squirrel.

Emmanuel

yazsaw7 a écrit :
Any other advice that you can offer to stop a particular build? I have a build that appears to be hung for more than 1 day.

i have restarted continuum and clicked 'Build All' and my build is still running in the background. I can still kick off new builds, but i can't stop the one build.

thx,
jason



Emmanuel Venisse wrote:
It's a known bug.

The workaround is:
- restart Continuum
- press the "build all" button at the bottom of the summary page

Emmanuel

Jerry DuVal a écrit :
Our server was restarted during a build and now Contiuum thinks the build is still running and will not start any other builds. Any way to clear continuum?