Dear all,

Captains: Please ensure this message reaches everyone in your club who is 
training on the Cam before the start of Michaelmas term.

We’ve received further details from the contractors carrying out the works at 
the Railway Bridge for the new Chisholm Trail Bridge. They expect to start 
carrying out piling from the bank from 2nd September. This will not impact 
navigation initially.

From Monday 9th September - Friday 13th September, 08:00-18:00, expect the 
river to be partially closed to 50% of its width. When this is the case, they 
will provide floating buoys around the works, signage up and downstream and 
bankmen up and down stream to let river users know what is occurring. Please 
cooperate with them to pass safely through the works.

From Monday 16th September - Friday 20th September and Monday 23rd September - 
Friday 27th September, 08:00-18:00, the river will need to be completely closed 
to all traffic at some times. When this is the case, they will provide a boom 
across the river with signage denoting the river is closed, plus signage 
further up and downstream and banksmen up and downstream to let people know 
what is occurring. They will not be fully closing the river past 18.00 nor 
before 08.00, however there may be 50% navigation restrictions outside those 
times, as well as between 08:00 and 18:00 (when the river isn’t closed 
completely), in which case they’ll have the same provisions as the 50% closure 
above. Again please cooperate with the banksmen to pass through safely when not 
completely closed.

They assure us that River closures will be kept to a minimum at all times.

We’ll keep you up to date with any schedule changes that may occur as soon as 
we hear about them.

Best wishes,
Conor