I hope everyone has enjoyed their summer vacations ... but now back to 
work! :) 

We do have a preliminary schedule for Luna milestones, see 
http://wiki.eclipse.org/Luna/Simultaneous_Release_Plan#Schedule
(though, that one table is only part of that document to review, at the 
moment). 

The complete schedule is still open for review and "tweaking", but the 
first several milestones are pretty much a given, and the first one is due 
in two weeks! The overall schedule (of having approximately 6 week 
milestones) is pretty much just like previous years. The one main 
difference is that we "moved up" M5 and M6 to make sure M6 finished before 
EclipseCon 2014 started (so ... we don't allow an "extra week" for 
end-of-year holidays) and this M5 and M6 change means M7 is a week longer 
than usual: 8 weeks instead of 7! 

As always, we hope everyone in 'kepler' stays in 'luna', but ... to make 
sure ... we require explicit "buy in". In practice, this means I started 
the 'master' branch with what ever it was for Kepler, but then set 
enabled="false" for everyone's contribution.  If you plan to be in Luna, 
please removed the enabled="false" from your "contribution element". If 
you are not quite ready to actually make a contribution, you can put 
enabled="false" in your "repository element" to signify the difference of 
"planning to participate", but "contribution not ready yet". If nothing 
else, you may simply have to wait until your pre-reqs make their 
contributions. 

I have enabled the contributions for Eclipse and Equinox (with out likely 
Luna M1 content), and produced a preliminary "staging" repo ... which has 
only those two projects in it, at the moment. 

Let the fun begin! As always, questions to this list are welcome. 

_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@eclipse.org
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev

Reply via email to