Not only is RC2 due "next week" (Wednesday's are the +3 days) ... we are 
in that part of the schedule where there is an RC every week, so less than 
3 weeks left to contribute anything to SR1 (9/18 is the last chance: RC4 
+3).  As always we hope everyone has good "ramp down" plans in place so 
the changes from RC to RC get fewer and fewer, reducing risks and 
improving overall stability. 

Be sure to keep everyone informed, by posting to this list, if anyone 
misses their +n day, or otherwise has any issues, or questions. 

http://wiki.eclipse.org/Kepler/Simultaneous_Release_Plan#SR1

Thanks, 