The planning council has settled on our complete schedule for the Mars 
release, and its service releases, including milestones, and other 
checkpoints. 

The most official source is the Plan, at 
http://wiki.eclipse.org/Mars/Simultaneous_Release_Plan#Schedule

but have also added them to our Planning Council Calendar, for your 
convenience. 

Plus, I have added the "Important Dates" provided by the Eclipse 
Foundation for their deadlines for Mars Release. (also pasted below)

All dates follow the same pattern as previous years, though there is one 
notable exception. M6 will be after EclipseCon this year (in 2015) rather 
than right before it. The reason is simply that EclipseCon has been moving 
"earlier in the year" by a few weeks, and the Planning Council felt M6 
could not be squeezed in before it, and thought it better to extend it a 
little so they did not coincide with each other. In the end, M5 is 7 weeks 
long, M6 is 7 weeks long, and M7 is 6 weeks long. Not a radical change, 
just wanted to mention it, in case anyone wanted to "show off" some new 
feature at EclipseCon, you would not automatically think you had "until 
M6" to get it done, as has been the case in previous years. 

Thanks everyone, 

= = = = = = = = = = = = 

Important Dates:
Feb 13/2015 - CQ Submission deadline for Mars
May 22/2015 - IP Log submission deadline
May 29/2015 - Review materials due
June 12/2015 - Release Review
_______________________________________________
cross-project-issues-dev mailing list
[email protected]
To change your delivery options, retrieve your password, or unsubscribe from 
this list, visit
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev

Reply via email to