"Zhao, Tina" <[email protected]> writes:

> QA plans to start Full testing today, but the latest Canary builds for
> both Xwalk Tizen and Android are published at 9/24.
>
> Do we have 9/27 canaries for both Xwalk Tizen and Android today?
>
> If the 9/27 canaries couldn’t be ready soon, QA will pick up the 9/24
> canaries for Weekly Full Testing this time.

Just to clarify to the others: the 9/27 canary is actually the one
generated on 9/26 (the build starts at 22:00 UTC).

Looking at the logs, it looks like both VMs had network connectivity
problems and couldn't finish their builds, so 1.29.8.0 is still the
latest canary.

If the network problems persist, I'll have to talk to our infrastructure
team once I arrive back to Finland.