The C1 landing process has again been extended till at least 12/3. We'll email 
in a week with any updates. I've updated 
https://etherpad.mozilla.org/b2g-convergence-schedule to reflect this change.

-Alex

On Nov 19, 2012, at 6:28 PM, Alex Keybl <[email protected]> wrote:

> [x-post to dev-b2g and dev-gaia]
> 
> We're now in the C2 milestone until 12/10, and plan to make sure that all 
> bugs meeting the C2 criteria are properly milestoned tomorrow. See 
> https://etherpad.mozilla.org/b2g-convergence-schedule for more info on the C2 
> criteria.
> 
> We've also updated https://etherpad.mozilla.org/b2g-convergence-landing to 
> extend the C1 landing process into at least the first week of C2. Moving to 
> approvals-only later in C2 is meant to help drivers vet the testing performed 
> on patches before landing, to prevent new major regressions that hurt ongoing 
> QA/dogfooding testing.
> 
> The more testing you all do, the less regressions we have, and the longer 
> we'll be able to extend the current landing process.
> 
> -Alex
> _______________________________________________
> dev-gaia mailing list
> [email protected]
> https://lists.mozilla.org/listinfo/dev-gaia

_______________________________________________
dev-b2g mailing list
[email protected]
https://lists.mozilla.org/listinfo/dev-b2g

Reply via email to