Dear b2g friends,

We are here to announce that we passed 2.2 Code Complete (CC) today Jun 8th. 

=Code Complete Status (As of 6/8 today)=
2.2+ all blockers (Must < 10)
http://mzl.la/1aImcbJ <http://mzl.la/1aImcbJ>
6 bugs up to today
MTBF (Must > 100 hrs)
Nexus 5: 105 hrs 
CAF status
Officially reached CS Milestone with the 5/27 build
MTBF sustained at 100+ hours 

=Post CC Action Plan= 
QA to send V2.2 Daily smoke report - FLAME-KK, NEXUS-5-L and V2.2 Weekly report
EPMs will help to continue triage for 2.2 rest blockers.
Any 2.1 / 2.0 landing that breaks QA smoketests needs to go through approval 
process to get it landed the second time on 2.1 / 2.0 branch. This applies to 
blocking-b2g:2.1+, blocking-b2g:2.0+ bugs as well. 

=Resources= 
Per team blockers : 
http://charts.mozilla.org/fxos/blockers.html#project=1.3T,1.4,2.0,2.1,2.2 
<http://charts.mozilla.org/fxos/blockers.html#project=1.3T,1.4,2.0,2.1,2.2>
CC criteria: http://mzl.la/1J7RrYS <http://mzl.la/1J7RrYS>
Branch/Landing information : 
https://wiki.mozilla.org/Release_Management/B2G_Landing 
<https://wiki.mozilla.org/Release_Management/B2G_Landing> 
https://wiki.mozilla.org/RapidRelease/Calendar 
<https://wiki.mozilla.org/RapidRelease/Calendar> 
Triage times and queries : https://wiki.mozilla.org/B2G/Triage#Triage_for_2.2.0 
<https://wiki.mozilla.org/B2G/Triage#Triage_for_2.2.0> 
We would also like to ask for your feedback of 2.2 retrospective : 
https://goo.gl/fKsvCy <https://goo.gl/fKsvCy>  (Thanks to EPMs!)
Your precious opinion is valuable for continuous improvement to our future 
release!

Thank you!
-------------------------------------------------------
Josh Cheng
Engineering Project Manager, Firefox OS
Mozilla Corporation
✉ [email protected] <mailto:[email protected]>
-------------------------------------------------------
_______________________________________________
dev-b2g mailing list
[email protected]
https://lists.mozilla.org/listinfo/dev-b2g

Reply via email to