https://issues.apache.org/jira/browse/AMBARI-9931?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=14348765#comment-14348765
]
Hudson commented on AMBARI-9931:
--------------------------------
ABORTED: Integrated in Ambari-branch-2.0.0 #8 (See
[https://builds.apache.org/job/Ambari-branch-2.0.0/8/])
AMBARI-9931 RU: upgrade dialog does not refresh with current tasks w/o browser
reload. (atkach) (atkach:
http://git-wip-us.apache.org/repos/asf?p=ambari.git&a=commit&h=45b8a093cf43db57cbfd984540ee72700f329e24)
* ambari-web/test/controllers/main/admin/stack_and_upgrade_controller_test.js
* ambari-web/app/views/main/admin/stack_upgrade/upgrade_group_view.js
* ambari-web/test/views/main/admin/stack_upgrade/upgrade_wizard_view_test.js
* ambari-web/app/templates/main/admin/stack_upgrade/upgrade_task.hbs
* ambari-web/app/controllers/main/admin/stack_and_upgrade_controller.js
* ambari-web/app/templates/main/admin/stack_upgrade/upgrade_group.hbs
* ambari-web/app/templates/main/admin/stack_upgrade/stack_upgrade_wizard.hbs
* ambari-web/app/views/main/admin/stack_upgrade/upgrade_wizard_view.js
> RU: upgrade dialog does not refresh with current tasks w/o browser reload
> -------------------------------------------------------------------------
>
> Key: AMBARI-9931
> URL: https://issues.apache.org/jira/browse/AMBARI-9931
> Project: Ambari
> Issue Type: Bug
> Components: ambari-web
> Affects Versions: 2.0.0
> Reporter: Andrii Tkach
> Assignee: Andrii Tkach
> Priority: Critical
> Fix For: 2.0.0
>
> Attachments: AMBARI-9931.patch
>
>
> Perform upgrade, dialog goes thru prepare tasks, I click to proceed. At that
> point, the % numbers move and I see progress in ambari-server.log but the UI
> list of tasks is not updating. It only shows Prepare task. Also, looks like
> things are coming back from REST API that show progress. It's the UI is just
> not updating.
> I reload my browser and then it catches up and starts showing tasks.
> What I notice: top level tasks don't show, I have to refresh browser, then
> the top-level will shows and the subs show.
> 1) So Prepare Backups shows
> 2) once PB is done, the next task does not show until I refresh browser
> 3) Then PB + ZooKeeper shows. once ZK is done, the next task does not show
> until I refresh browser
> 4) Then PB + ZK + Core Masters shows. once CM is done, the next task does
> not show until I refresh browser
> I see this this for all top-level tasks.
--
This message was sent by Atlassian JIRA